[09:57, 01/03/2024] Azman HKL: Welcome Mr. Frankie from Venus Pool to EGMall site coordination group.
[09:57, 01/03/2024] Kadapi J. PROMES: Aku cuti ni hari guys.
[16:29, 01/03/2024] Azman HKL: Reminder tomorrow safety meeting on site ya. Site PIC please attend
NSC GROUP
[08:52, 01/03/2024] Azman HKL: Morning. @HIDAYA KH office Num minta tutup itu semua proper tutup itu pipe yang keluar. ππ
[08:53, 01/03/2024] Azman HKL: Sewer pipe dan Man Hole akan maw start jalan. Kita liaise sama Kinnangland ya di site untuk inlet pipe masuk man hole.
[09:19, 01/03/2024] HIDAYA KH office Num: okay2
[09:49, 01/03/2024] Azman HKL: We share Tower A hotel 4 wall setting from Econmech.
[09:49, 01/03/2024] Azman HKL: This is for 8th - 9th floor.
[09:50, 01/03/2024] Azman HKL: @~Julian Kloneles @King Hong Office please study. @~ShawnChia @HIDAYA KH office Num please advise as per our discussion on site.
[09:54, 01/03/2024] Azman HKL: New Slab Casting Plan
4F - TB4 - 05/3/24
@~.Fazli @~WY @HIDAYA KH office Num please plan accordingly. π