Monday, January 8, 2024

9 JAN 2024 HKL


SITE EG MALL

[08:54, 09/01/2024] Azman HKL: 11th floor. TA2. @Kadapi J. PROMES Request for inspection today. Slab M&E services at 10-11 am. Site PIC during inspection please standby on site. TQ.
[09:51, 09/01/2024] Kadapi J. PROMES: Other NSC have to do like thisπŸ™‚
[09:53, 09/01/2024] Kadapi J. PROMES: πŸ€”


[10:26, 09/01/2024] Azman HKL: Pre task briefing. Lifting crew.

[10:27, 09/01/2024] Azman HKL: Genset & Transformer lift to 6th floor in progress.

NSC GROUP

[08:45, 09/01/2024] Azman HKL: Site progress photo.
9/1/24.
11th floor. TA2. Slab cleaning in progress. 12th floor. TA1. Slab formwork in progress.


[08:45, 09/01/2024] Azman HKL: 4th floor. Ramp. Formwork in progress. 5th floor. Z7. Slab formwork in progress. 6th floor. Z6. Slab rebar work in progress.

[08:45, 09/01/2024] Azman HKL: Basement. Z10. Slab foundation rebar works in progress.

[08:45, 09/01/2024] Azman HKL: Basement. Z9. Lift wall rebar in progress

[09:09, 09/01/2024] Azman HKL: DCC lorry crane on site to start transfer and lift Genset & transformer equipment 

[10:28, 09/01/2024] Azman HKL: Genset & Transformer equipment lift to 6th floor in progress.
[10:30, 09/01/2024] +60 12-559 6863: @Azman HKL once hoisted to 6F shift it to G/L H-I/5-8 (to confirmed with Lo for exact location), don't keep at G/L K-L as we need to prepare for 7F casting at that area so that these equipment can be stored there later

[10:58, 09/01/2024] Azman HKL: Cant shift it by today. All column rebar were built and kept there. @Lo. W. H (HKL-Site Engineer) we need to find other place for GnB to built this column..

[11:10, 09/01/2024] Azman HKL: 11th floor. TA2. M&E services in slab inspection in progress.

[15:21, 09/01/2024] Azman HKL: New Casting Plan
11F - TA/2 - 9/1/24
12F - TA/1 - 12/1/24
12F - TA/2 - 16/1/24
BF - Z9C - 9/1/24
BF - Z11/1 - 13/1/24
3F - TB/4 - 15/1/24
5F - Z7 - 15/1/24
4F - Ramp6 - 11/1/24

Please take note and plan. Any changes will be informed.
[17:32, 09/01/2024] Edwin Chen 013: Drop alignment out
[17:35, 09/01/2024] Azman HKL: @~nas4rie nanti pg check dia. πŸ‘†

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...