Friday, February 9, 2024

9 FEB 2024 HKL

 NSC GROUP



[08:55, 09/02/2024] Azman HKL: Site progress photo.
9/2/24.
15th floor. TA1. Transfer beam rebar and slab formwork in progress.

[08:55, 09/02/2024] Azman HKL: 14th floor..TA2. lift wall rebar and column work in progress. 15th floor scaffolding support in progress.

[09:22, 09/02/2024] Azman HKL: Ground floor. @~Leppong @~WY boleh sda potong bata. Keluar sda org didalam.