[09:34, 07/02/2024] Kadapi J. PROMES: Walker, please paint antyrust for any brackets b 4 they laying bricks at risers staircase area. Tq
[09:35, 07/02/2024] Kadapi J. PROMES: This one at level 4 st9
[14:38, 07/02/2024] Azman HKL: Request for inspection. Ground floor. Z8. 3pm. @Kadapi J. PROMES. PIC please standby at site during inspection. TQ.π
NSC GROUP
[10:24, 07/02/2024] Azman HKL: 15th floor. TA1. Slab formwork and transfer rebar in progress.
[10:24, 07/02/2024] Azman HKL: 14th floor. TA2. Column rebar in progress.
[10:24, 07/02/2024] Azman HKL: 1st floor. TB6. Slab formwork, beam rebar and M&E work in progress.
[10:24, 07/02/2024] Azman HKL: Ground floor. Z8. Slab rebar and&E in progress
[11:41, 07/02/2024] Azman HKL: New casting plan
15F - TA/1 CJ - 13/2/24
15F - TA/1 slab - 20/2/24
15F - TA/2 Column - 8/2/24
15F - TA/2 slab - 23/2/24
1F - TB6 - 8/2/24
GF - Z8 - 7/2/24
Please take note and plan. Any changes will be informed.
[14:58, 07/02/2024] Azman HKL: Ground floor. Z8. M&E inspection in progress.
[15:45, 07/02/2024] Azman HKL: Done inspection. Please proceed. @Mr. Voo . π
[15:55, 07/02/2024] Mr. Voo: ππ»