[08:52, 27/02/2024] Azman HKL: Site progress photo.
27/2/24.
2nd floor. TB6. Slab rebar and M&E in progress.
[08:52, 27/02/2024] Azman HKL: 7th floor. Zone 7PA. Slab rebar and M&E in progress.
[08:52, 27/02/2024] Azman HKL: 16th floor. TA1. Slab formwork in progress. 15th floor. TA2. Column and lift rebar in progress.
[08:55, 27/02/2024] Azman HKL: 6th floor. Z7. Slab cast.
[10:30, 27/02/2024] Azman HKL: 7th floor. Zone P7a. Joint inspection of escalator slab opening with Mitsubishi and. Consultant.
[11:21, 27/02/2024] Azman HKL: 7th floor. Joint inspection escalator opening.