[14:55, 26/01/2024] Azman HKL: 13th floor. TA2. Request for inspection at 3.30pm. @Kadapi J. PROMES . PIC please stand by at site during inspection.
NSC GROUP
[09:19, 26/01/2024] Mr. Voo: @HIDAYA KH office Num tolong atur bungkus semua ni pipe , maw timbun ni ..
[09:20, 26/01/2024] HIDAYA KH office Num: okay2
[09:20, 26/01/2024] Mr. Voo: Thxs
[09:25, 26/01/2024] Azman HKL: Site progress photo.
26/1/24.
13th floor.. TA2. Slab rebar and M&E in progress.
[09:25, 26/01/2024] Azman HKL: 14th floor. TA1.slab formwork and scaffolding work in progress.
[09:25, 26/01/2024] Azman HKL: 6th floor. Z7. Slab formwork in progress. Z6. Lift wall formwork and column work in progress.
[09:28, 26/01/2024] Azman HKL: @~WY please update your daily manpower. 🙏.
[10:06, 26/01/2024] HIDAYA KH office Num: done
[15:01, 26/01/2024] Azman HKL: Okay noted. @HIDAYA KH office Num @~Leppong @~WY tolong ya. Tempat kerja mesti kasi bersih. Minta ya kerjasama.
[16:24, 26/01/2024] HIDAYA KH office Num: @Azman HKL minta tolong clear. esok pagi mau jalan pipe sini. tqtq 🙏🏼
[16:29, 26/01/2024] Azman HKL: 1st floor ka?
[16:30, 26/01/2024] HIDAYA KH office Num: ground floor
[16:35, 26/01/2024] Azman HKL: Situ saja ka? Sy inform Subcon. Mungkin bsok pagi tidak dapat tu. Mungkin ahad atau isnin tu. Saya inform mereka saja dulu.
[16:39, 26/01/2024] HIDAYA KH office Num: ini seja
[16:44, 26/01/2024] Azman HKL: Ok..👌