23 FEB 2024 HKL

 NSC GROUP


[14:15, 23/02/2024] Azman HKL: Site progress photo.
23/2/24.
2nd floor. TB6. Slab formwork and  rebar in progress.

[14:15, 23/02/2024] Azman HKL: 16th floor. TA2. Slab formwork in progress. 15th floor. TA2. Slab cast.

[14:15, 23/02/2024] Azman HKL: 6th floor. Slab formwork in progress.

[14:15, 23/02/2024] Azman HKL: 1st floor. Z8. Slab cast.
[15:17, 23/02/2024] Azman HKL: 4th flooor. ST9. @~WY orang pasang ducting ada sampai sda? Tolong ya ini ducting, supaya subcon bata boleh jalan. Tolong ikut semua komen dari konsultan supaya tdk di reject.🙏
[15:28, 23/02/2024] +60 12-843 3877: Relocate trunking to new MSB room @Besment
[15:44, 23/02/2024] Azman HKL: 6th floor. Genset plinth cast.