Tuesday, February 20, 2024

20 FEB 2024 HKL

 NSC GROUP


[08:31, 20/02/2024] Azman HKL: Site progress photo.
20/2/24.
15th floor. TA2. Slab rebar and M&E in progress.

[08:31, 20/02/2024] Azman HKL: 2nd floor. TB6. Slab formwork in progress

[08:31, 20/02/2024] Azman HKL: 1st floor. Z8. Slab formwork and beam rebar in progress.

[08:56, 20/02/2024] Azman HKL: 1st floor. Z8. Slab bottom bar in progress.

[08:59, 20/02/2024] Azman HKL: 1st floor. BL4. Service suite lift. Button lift opening done.

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...