[08:51, 19/02/2024] Azman HKL: Site progress photo.
19/2/24.
15th floor. TA1. Slab cast. TA2. Slab formwork inprogress.
[08:53, 19/02/2024] Azman HKL: 1st floor. Z8. Slab formwork in progress.
[08:53, 19/02/2024] Azman HKL: 2nd floor. TB6. Slab formwork in progress
[11:18, 19/02/2024] Azman HKL: Tomorrow coordination meeting at 3.30pm. At basement.
@~ShawnChia @HIDAYA KH office Num @Dart Econmech
[11:28, 19/02/2024] Azman HKL: To All Site Personnel & Teams,
Please arrange sufficient manpowers to have the access and staircase leading to Tower A are clear of obstruction like debris, formworks, scaffoldings and etc..
#Priorities : Level 7 - 10 of Tower A; because target 19/02/2024, Monday onwards, Datuk Sri from Client will be coming for site visit..
Please take note ya.. as informed from consultant side just now..
@~nas4rie @Jimmy HKL @+60 16-776 5594 @+60 17-716 3213 @+60 14-286 1618
CC : @Azman HKL @~π
πΆπ ππ½πππ @Mr. Voo
[11:30, 19/02/2024] Azman HKL: @~Leppong @HIDAYA KH office Num @~WY tolong pastikan semua pekerja pakai PPE, dan jaga housekeeping di tempat kerja dan tempat rehat.
[13:45, 19/02/2024] Azman HKL: 15th floor. TA2. Slab rebar in progress.
[15:00, 19/02/2024] Azman HKL: ST2. Retaining wall. @~WY check if any conduit to installed before they close. π