[08:55, 16/01/2024] EG MALL ECONMECH Dart: @Azman HKL morning man. Supermarket basement area kami mau start pasang spk pipe. Any plumbing pipe d sana belum pasang?
[08:56, 16/01/2024] HIDAYA KH office Num: morning dart. pipe kami di basement on progress sekarang
[09:03, 16/01/2024] EG MALL ECONMECH Dart: Bha kta sma2 jalan dan better we coordinate first ya
[09:04, 16/01/2024] HIDAYA KH office Num: okay dart
[09:20, 16/01/2024] Kadapi J. PROMES: Better come to site and discuss together
[09:20, 16/01/2024] Kadapi J. PROMES: Bring the latest drawing
[09:21, 16/01/2024] EG MALL ECONMECH Dart: bha ok mr kadapi
[09:21, 16/01/2024] Kadapi J. PROMES: What tome you guys free?
[09:21, 16/01/2024] Kadapi J. PROMES: #time
[09:51, 16/01/2024] Azman HKL: Cant join today. MC. If I can, we meet tomorrow. 10am morning.
NSC GROUP
[08:08, 16/01/2024] Azman HKL: Site progress photo.
16/1/24.
12th floor. TA2. Slab rebar, formwork and M&E in progress.
[08:08, 16/01/2024] Azman HKL: 12th floor. TA1. Column rebar in progress.
[08:45, 16/01/2024] Azman HKL: 4th floor ramp, beam rebar. 5th floor, Z7. Slab beam rebar in progress. 6th floor, Z6. Slab rebar inprogress.
[08:45, 16/01/2024] Azman HKL: Ground floor. TB6. Slab formwork in progress. Basement, teyaining wall rebar in progress