SITE EG MALL
[10:38, 16/02/2024] +60 16-880 4632: @~Roxas Ng (Kai) @EG MALL Mr Lo
Please arrange without further delay..
[10:39, 16/02/2024] +60 16-832 2597: Ok noted sir, arrange asap
[10:42, 16/02/2024] +60 16-880 4632: Column Chamfer edge prefer saw cut instead of hacking...
[11:38, 16/02/2024] +60 16-880 4632: @EG MALL Mr Lo @~Roxas Ng (Kai)
Please take necessary action without further delay..
[11:42, 16/02/2024] +60 16-880 4632: @~Roxas Ng (Kai) please arrange the remaining plastering works
Internal side of Riser compartments...
[11:42, 16/02/2024] +60 16-832 2597: Noted sir
[11:45, 16/02/2024] +60 12-559 6863: @~Johnny we will take note and rectify your comments one by one, can’t do everything in the same time. Hope u understand
[11:50, 16/02/2024] +60 16-880 4632: @~π
πΆπ ππ½πππ
fully understanding we need same one to monitor...skim coating in progress at column..
[11:50, 16/02/2024] +60 12-559 6863: Thank uπ
NSC GROUP
[09:28, 16/02/2024] Azman HKL: Morning. @HIDAYA KH office Num . Boleh kasi keluar nanti tu tong supaya boleh sapu water proof tu plinth sekali. Alang2.. kalau dapat bsok dia org sapu waterproof.
[09:30, 16/02/2024] HIDAYA KH office Num: morning. okay kami alihkan kejap lagi
[09:35, 16/02/2024] Azman HKL: TQ.π
[09:40, 16/02/2024] Azman HKL: Basement. @~WY @HIDAYA KH office Num sini ada crossing ducting dan PVC pipe. Bila senang kita maw koordinat sini. Jam 10am.
[09:40, 16/02/2024] HIDAYA KH office Num: okay boleh. jam 10
[10:14, 16/02/2024] Azman HKL: Basement joint inspection
[10:14, 16/02/2024] Azman HKL: Basement joint inspection.
[10:52, 16/02/2024] Azman HKL: Site progress photo.
16/02/24.
15th floor. Slab rebar and M&E. 14th floor. Column and lift rebar.
[10:52, 16/02/2024] Azman HKL: 1st floor. Z8. Slab formwork in progress
[10:52, 16/02/2024] Azman HKL: 2nd floor. TB6. Slab formwork in progress