Saturday, January 13, 2024

14 JAN 2024 HKL

NSC GROUP

[08:54, 14/01/2024] Azman HKL: Site progress photo
14/1/24.
12th floor. TA1. Column rebar in progress. TA2. Slab formwork in progress.

[08:54, 14/01/2024] Azman HKL: 4th floor. Ramp. Beam rebar in progress. 5th floor. Z7.  Slab/ beam rebar. 6th floor. Z6. Slab rebar

No comments:

Post a Comment

  EGMALL COORDINATION (6 18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation. 18th floor. Tow...