Tuesday, February 13, 2024

13 FEB 2024 HKL

SITE EG MALL 


[10:36, 13/02/2024] Kadapi J. PROMES: Level 15 office now status

[14:13, 13/02/2024] +60 12-843 3877: Installatoin pvc conduit @level 15_slab was done



 NSC GROUP 

[08:55, 13/02/2024] Azman HKL: Site progress photo.
13/2/2024
15th floor. TA1. Transfer beam formwork, slab rebar and M&E in progress

[08:55, 13/02/2024] Azman HKL: 14th floor. TA2. Lift wall formwork and column work in progress.

[08:55, 13/02/2024] Azman HKL: 1st floor. Z8. Slab formwork in progress.

[08:55, 13/02/2024] Azman HKL: 2nd floor. TB6. Slab formwork in progress