[08:22, 02/02/2024] Azman HKL: Site progress photo.
2/2/2024.
14th floor. TA1. Column rebar and formwork in progress. TA2. Slab formwork, plumbing pipe and slab rebar in progress.
[08:22, 02/02/2024] Azman HKL: 1st floor. TB6. Slab formwork in progress. Ground floor. Lift wall and retaining wall in progress.
[08:22, 02/02/2024] Azman HKL: 6th floor. Z7 & Z6. Column rebar in progress. 5th floor. Ramp 7. Slab formwork in progress.
[08:31, 02/02/2024] Azman HKL: Basement. Transformer stored at the transformer room
[14:20, 02/02/2024] Azman HKL: 14th floor. TA2. Slab rebar and M&E in progress.
[14:20, 02/02/2024] Azman HKL: 1st floor. TB6. Slab formwork in progress