Thursday, February 1, 2024

02 FEB 2024 HKL

SITE EG MALL








[15:02, 02/02/2024] +60 12-843 3877: Istallation pvc conduit@level 14_column&slab in progress

NSC GROUP

 [08:22, 02/02/2024] Azman HKL: Site progress photo.
2/2/2024.
14th floor. TA1. Column rebar and formwork in progress. TA2. Slab formwork, plumbing pipe and slab rebar in progress.

[08:22, 02/02/2024] Azman HKL: 1st floor. TB6. Slab formwork in progress. Ground floor. Lift wall and retaining wall in progress.

[08:22, 02/02/2024] Azman HKL: 6th floor. Z7 & Z6. Column rebar in progress. 5th floor. Ramp 7. Slab formwork in progress.

[08:31, 02/02/2024] Azman HKL: Basement. Transformer stored at the transformer room

[14:20, 02/02/2024] Azman HKL: 14th floor. TA2. Slab rebar and M&E in progress.


[14:20, 02/02/2024] Azman HKL: 1st floor. TB6. Slab formwork in progress






No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...