Monday, January 1, 2024

2 JAN 2024 HKL



 NSC GROUP 

[10:00, 02/01/2024] Azman HKL: 11th floor. TA1. Slab formwork in progress. Column rebar in progress.

[10:00, 02/01/2024] Azman HKL: 10th floor. TA2. slab cast

[10:00, 02/01/2024] Azman HKL: 4th floor. Z7. Column rebar in progress. 6th floor. Z6. Slab rebar and M&E in progress.

[10:00, 02/01/2024] Azman HKL: Basement. Slab rebar in progress.
[14:11, 02/01/2024] Azman HKL: Today Coordination meeting. 
2/1/2023. 3.30pm at the site meeting room.
[14:11, 02/01/2024] +60 16-837 8881: 👌🏻

[14:50, 02/01/2024] Azman HKL: 7th floor. Connecting slab. Slab rebar in progress.
[15:14, 02/01/2024] Azman HKL: New Casting Plan
7F - Con. Slav - 4/1/24
11F - TA/1 - 5/1/24
11F - TA/2 - 8/1/24
3F - TB/4 - 12/1/24
6F - TB/5 - TBU
6F - TB/3 - TBU
BF - 5C - TBU
BF - Z9 - TBU (this week)
BF - Z11/1 - TBU 
Please take note and plan. Any changes will be informed.

[15:48, 02/01/2024] Lo. W. H (HKL-Site Engineer): tower A 14th floor

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...