Wednesday, December 13, 2023

13 DEC 2023 HKL

 NCS GROUP 


[09:53, 13/12/2023] Azman HKL: Site progress photo.
13/12/2023.
5th floor. TB5. Slab formwork and rebar in progress

[09:53, 13/12/2023] Azman HKL: Basement. Z9c. Retaining wall rebar, lift pit rebar in progress.

[09:53, 13/12/2023] Azman HKL: Basement. 5C. Slab foundation rebar i. Progress.

[09:53, 13/12/2023] Azman HKL: 7th floor. Z4. Beam rebar in progress.

[10:06, 13/12/2023] Azman HKL: Basement. Formwork dismantling in progress.

[10:09, 13/12/2023] Azman HKL: 9th floor. TA1. Slab formwork in progress. 8th floor. Lift wall formwork in progress

[10:33, 13/12/2023] Azman HKL: @HIDAYA KH office Num sini basement. Nanti jumpa sama Joseph, tolong alih dia mana2 barang yang blok kerja bata dia. 🙏🙏

[14:26, 13/12/2023] Azman HKL: 9th floor. TA1. Slab formwork in progress.

[14:26, 13/12/2023] Azman HKL: 5th floor. TB5. Slab rebar in progress

[14:26, 13/12/2023] Azman HKL: 8th floor. TA/2 Lift wall internal formwork in progress.

[14:26, 13/12/2023] Azman HKL: TB3, column rebar in progress.

[15:12, 13/12/2023] Azman HKL: Temporary lift storage inspection with Mitsubishi at ground floor.