Wednesday, November 29, 2023

30 NOV 2023 HKL

 NSC GROUP

[09:45, 30/11/2023] Azman HKL: 6th floor partial slab detail.


[09:53, 30/11/2023] Azman HKL: Site progress photo. 
30/11/2023.
4th floor. TB5. Slab cast

[09:53, 30/11/2023] Azman HKL: 8th floor. TA1. Slab formwork in progress.

[09:53, 30/11/2023] Azman HKL: 3rd floor. Z7. Slab formwork in progress.

[09:56, 30/11/2023] Azman HKL: 7th floor. TA2. Slab formwork in progress.

[09:57, 30/11/2023] Azman HKL: 5th floor. Z6. Column formwork inprogress.

[10:34, 30/11/2023] Azman HKL: Basement. Z9a. Retaining wall rebar in progress.
[10:36, 30/11/2023] Raymond Chong. Y. F (HKL P. Manager): King Hong ada pipe sleeve kat situ ka?
[10:48, 30/11/2023] HIDAYA KH office Num: ada. will install pipe sleeves in beam later

[11:06, 30/11/2023] Azman HKL: 1st floor. ST6. Wet riser pipe and LPD. Please get the installation approval from the consultant. @~Walker Yapi 🙏

[15:39, 30/11/2023] Azman HKL: Kena pipe st5  2nd floor
[15:40, 30/11/2023] Azman HKL: @HIDAYA KH office Num nanti tolong check ya..


No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...