Wednesday, December 20, 2023

21 DEC 2023 HKL


SITE EG MALL 

[11:29, 21/12/2023] Azman HKL: 9th floor. TA2. Request for inspection today at 3pm M&E cast in slab services. @Kadapi J. PROMES . NSC PIC please stanby on site with RFI form and latest drawing. πŸ™


NSC GROUP

[08:33, 21/12/2023] Azman HKL: Morning. Basement, fire watertank. @HIDAYA KH office Num please check this incoming water from your pipe sleeve and how to stop the water from coming to the water tank area. πŸ™πŸ™
[08:34, 21/12/2023] HIDAYA KH office Num: okay2 will check soon
[08:48, 21/12/2023] Lo. W. H (HKL-Site Engineer): dear valued NSC, there will be amendment to the layout at tower A, 10th floor and above (hotel section)
[08:48, 21/12/2023] Lo. W. H (HKL-Site Engineer): official drawing from architect not yet release
[08:49, 21/12/2023] Lo. W. H (HKL-Site Engineer): the above drawing shared by EG
[08:49, 21/12/2023] Lo. W. H (HKL-Site Engineer): please study accordingly in related to your job scope
[09:21, 21/12/2023] Edwin Chen 013: Riser qty reduce from 16 to 12? Space might be not enough
[09:56, 21/12/2023] Azman HKL: Good morning. 
21/12/2023.
9th floor. TA2. Slab rebar and M&E in progress.
[09:56, 21/12/2023] Azman HKL: 9th floor. TA2. 10th floor scaffolding support in progress.

[09:58, 21/12/2023] Azman HKL: 6th floor. TB3. Slab rebar and M&E in progress.


[10:01, 21/12/2023] Azman HKL: 3rd floor. Z7. And ramp 4. Slab form work and rebar in progress.

[10:01, 21/12/2023] Azman HKL: 7th floor. Z4. Slab rebar, formwork and M&E in progress.

[10:57, 21/12/2023] Dart Econmech: @Azman HKL man. Banyak nyamuk d basement. Pls do some control πŸ™πŸ»
[11:11, 21/12/2023] Azman HKL: @Jimmy HKL nanti kita tgk mcm kita boleh bikin ini. πŸ‘†
[11:11, 21/12/2023] Jimmy HKL: okay
[11:16, 21/12/2023] HIDAYA KH office Num: semua floor🦟🦟


[13:20, 21/12/2023] Lo. W. H (HKL-Site Engineer): Dear valued NSC, we have officially received the revised drawing of 10th floor -13th floor....
[13:20, 21/12/2023] Lo. W. H (HKL-Site Engineer): please study the layout accordingly
[13:21, 21/12/2023] Lo. W. H (HKL-Site Engineer): especially king hong
[13:36, 21/12/2023] Edwin Chen 013: "It may enhance collaboration if the latest revised official drawing is shared via email, ensuring all relevant parties are aligned and updated. This practice fosters better communication and provides a reference point for any future problems or discussions.
[15:44, 21/12/2023] Lo. W. H (HKL-Site Engineer): Dear valued NSC, the amendment of structure in comply to architect's amendment at 10th floor and above

[15:59, 21/12/2023] Azman HKL: 9th floor. TA2. M&E services inspection in progress..
[16:25, 21/12/2023] Azman HKL: Tolong ya M&E NSC, lepas kerja housekeeping tempat kerja juga ya.
[16:39, 21/12/2023] Azman HKL: @~nas4rie @Mr. Voo 9th floor. TA2. Please proceed


No comments:

Post a Comment

EG MALL SITE DAILY (15 NOV 2024)

     EG MALL SITE DAILY (15 NOV 2024)