Tuesday, December 19, 2023

20 DEC 2023 HKL

 NSC GROUP 


[08:14, 20/12/2023] Azman HKL: Good morning. 
Site progress photo. 20/12/2023.
9th floor. TA2. Slab rebar and M&E in progress. TA1. 10th floor slab scaffolding support in progress.

[08:16, 20/12/2023] Azman HKL: 4th floor. Z7. Slab formwork in progress. 3rd floor, ramp 4. Ramp formwork and beam rebar in progress.
[08:25, 20/12/2023] Azman HKL: Dear NSC please update latest of your work progress for this week report and forward to me. Thanks.
[08:26, 20/12/2023] Azman HKL: @~ShawnChia @Recky Econmech @HIDAYA KH office Num

[09:11, 20/12/2023] Azman HKL: 9th floor. TA2. 10nos DCC man power to install conduit on slab in progress.

[09:36, 20/12/2023] HIDAYA KH office Num: morning. @Azman HKL  for info. ini king hong punya
[09:58, 20/12/2023] Azman HKL: Ok.
[09:58, 20/12/2023] Azman HKL: Ada tulis nama bah kan.
[09:59, 20/12/2023] HIDAYA KH office Num: ada juga

[10:15, 20/12/2023] Mr. Voo: Tu pipe tak urgent jangan pasang dulu .. nanti sya cabut sheet pipe patah semua tu ..
[10:16, 20/12/2023] Mr. Voo: @Azman HKL  suruh kasih buka dulu
[10:16, 20/12/2023] Mr. Voo: Backfill pun susah

[10:16, 20/12/2023] Azman HKL: 6th floor. TB3. Beam rebar in progress.

[10:16, 20/12/2023] Azman HKL: 7th floor. Z4. Slab rebar and M&E in progress.
[10:19, 20/12/2023] Azman HKL: @HIDAYA KH office Num tolong pg check sana mana yang kena sheetpile.

[13:40, 20/12/2023] Azman HKL: 9th floor. TA2. Conduit in progress.

[15:07, 20/12/2023] +60 12-843 3877: Ini ELE riser belum ada form wood,kami banyak mau buat opening@@Azman HKL
[15:12, 20/12/2023] Azman HKL: Ok. Saya inform mereka.
[15:42, 20/12/2023] Azman HKL: M&E progresses until 20.12.23. please check and comment if any changes for tomorrow's report. TQ