SITE EG MALL
[14:28, 15/12/2023] Azman HKL: Request for inspection. 1. Sump pit dimension, 2. Fire water tank and pump plinth layout at 3pm. @Kadapi J. PROMES NSC. @HIDAYA KH office Num @~Walker Yapi please stanby with RFI and latest drawing.
NSC GROUP
[08:36, 15/12/2023] Azman HKL: Good morning.
15/12/2023.
Site progress photo.
9th floor. TA1. Slab rebar and M&E in progress. TA2. Column rebar and slab scaffolding support in progress
[08:36, 15/12/2023] Azman HKL: Basement. Z5C. Slab foundation and plinth rebar in progress.
[08:42, 15/12/2023] HIDAYA KH office Num: @60128433889 morning. we request to clear this area. our installations works pending for room 9,10,11 due to this kind of site condition.
[08:43, 15/12/2023] Azman HKL: 5th floor. TB5. Slab rebar and M&E in progress.
[09:13, 15/12/2023] Azman HKL: @HIDAYA KH office Num tolong atur ni barang di basement. Jumpa sama Joseph tanya dia mana2 barang yang ganggu kerja dia.
[09:14, 15/12/2023] HIDAYA KH office Num: suda jumpa. kami tengah kasi pindah sekarang
[09:14, 15/12/2023] Azman HKL: Ok. TQ.👌
[10:49, 15/12/2023] Azman HKL: New Casting Plan
BF - 9B RC wall - 14/12/23
BF - 9C -15/12/23
BF - 5C/a - 15/12/23
9F - TA/1 - 17/12/23👈
6F - TB5 - 16/12/23
6F - Z6 - 23/12/23👈
9F - TA/2 -21/12/23
6F - TB3 - 21/12/23
4F - Z7 - 21/12/23
6F - Z4 - 26/12/23
Ramp4 - 21/12/23
👈=Changes
Please coordinate material, man power and drawing onsite. Date may be changed due to site condition.
No comments: