[13:54, 09/12/2023] Azman HKL: 5th floor. TB3. Request for inspection. M&E services cast in slab 2pm. @Kadapi J. PROMES . PIC please stand by RFI form.
NSC GROUP
[08:59, 09/12/2023] Azman HKL: Morning. @~Walker Yapi @HIDAYA KH office Num 8th floor sekarang sedang housekeeping ya. Nanti surveyor akan naik sana marking kamu boleh pasang itu box sama sleeve.
[09:00, 09/12/2023] HIDAYA KH office Num: morning. okay azman. inform saja klu surveyor mau start suda. kami standby awal
[09:14, 09/12/2023] Azman HKL: Site progress photo.
9/12/2023.
8th floor. TA1. Slab formwork and housekeeping.
[09:14, 09/12/2023] Azman HKL: 5th floor. TA2. Slab rebar and M&E in progress.
[09:14, 09/12/2023] Azman HKL: Basement, Z8. Earthwork in progress.
[09:33, 09/12/2023] Azman HKL: 3rd floor Cold water pump room. @~Roxas Ng (Kai) also request screeding and plastering to this room.
[09:35, 09/12/2023] Azman HKL: 👆 request plastering and screeding .
[10:03, 09/12/2023] Azman HKL: 8th floor. Housekeeping in progress..
[11:22, 09/12/2023] Azman HKL: @~Walker Yapi @HIDAYA KH office Num sda marking di papan. Study tu layout ya jangan salah.
[11:22, 09/12/2023] Azman HKL: Ini marking di slab surveyor sda buat.
[15:35, 09/12/2023] HIDAYA KH office Num: surveyor will check and confirm layout
[16:10, 09/12/2023] Azman HKL: 5th floor. TB3. M&E inspection done. @Mr. Voo @~nas4rie please proceed. 👌
[16:11, 09/12/2023] Mr. Voo: 👍🏻
[17:43, 09/12/2023] Azman HKL: @Lo. W. H (HKL-Site Engineer) @HIDAYA KH office Num ini flow trap scupper drain rendah. Maw tenggelam simen..
[17:43, 09/12/2023] Azman HKL: Maw ubah ka?
[17:43, 09/12/2023] Lo. W. H (HKL-Site Engineer): Ubah
[17:45, 09/12/2023] Mr. Voo: 1758