Thursday, December 7, 2023

08 DEC 2023 HKL

SITE EG MALL 

[14:46, 08/12/2023] Azman HKL: 7th floor. TA2. Request for inspection. M&E services are cast in slab. 3.00pm. @Kadapi J. PROMES .

NSC GROUP




[08:53, 08/12/2023] HIDAYA KH office Num: morning. mau request kasi clear 8F TA2. kami mau start
 pipe sleeves installation pagi ni. @Azman HKL

[08:54, 08/12/2023] Lo. W. H (HKL-Site Engineer): please take photo of the ft @HIDAYA KH office Num 7th floor which to plan cast today
[08:54, 08/12/2023] Lo. W. H (HKL-Site Engineer): thanks
[08:54, 08/12/2023] Lo. W. H (HKL-Site Engineer): when you free

[08:58, 08/12/2023] HIDAYA KH office Num: ☝🏼


[08:58, 08/12/2023] HIDAYA KH office Num: 5th floor TB5

[09:04, 08/12/2023] Lo. W. H (HKL-Site Engineer): ft yang scupper drain 300x150
[09:04, 08/12/2023] Lo. W. H (HKL-Site Engineer): @HIDAYA KH office Num 😅
[09:06, 08/12/2023] HIDAYA KH office Num: this one
[09:06, 08/12/2023] HIDAYA KH office Num: and this one
[09:08, 08/12/2023] Lo. W. H (HKL-Site Engineer): ooo make sure it's align with the scupper drain path
[09:12, 08/12/2023] Azman HKL: Okay. Ini sabar, mereka clear juga tu. Nanti sebelum besi saya minta dulu Laisam tembak lantai atur itu bilik2 untuk kamu masuk duluan. Ini 8th floor 11/12/23.
[09:13, 08/12/2023] HIDAYA KH office Num: okay

[13:34, 08/12/2023] Edwin Chen 013: Any indication when can start the works on the 3rd floor water tank area? @Azman HKL
[14:09, 08/12/2023] Azman HKL: Wall plastering and floor screeding will start and hopefully complete by next week. After that the wall undercoat and water tank can start. I will liaise with @~Roxas Ng (Kai) to push this to complete.
[14:27, 08/12/2023] Edwin Chen 013: Hope can expedite, our worker will finish Basement tank soon