[13:56, 07/12/2023] +60 12-843 3877: Installation pcv cable_95mm size for Earthing /Lightning system@besment
NSC GROUP
[09:33, 07/12/2023] Azman HKL: New Casting Plan
8F - TA/1 - casted
5F - TB3 - 7/12/2023
BF - 9B RC wall - 7/12/2023
7F - TA/2b - 8/12/2023
8F - TA/2 - 10/12/2023
5F - TB/5 - TBU
6F -Z6 - TBU
8F - TA/1 - casted
5F - TB3 - 7/12/2023
BF - 9B RC wall - 7/12/2023
7F - TA/2b - 8/12/2023
8F - TA/2 - 10/12/2023
5F - TB/5 - TBU
6F -Z6 - TBU
Please coordinate material, man power and drawing onsite. Date may be changed due to site condition.
[10:29, 07/12/2023] Mr. Voo: @Leung KH🍀
[10:29, 07/12/2023] Mr. Voo: Is ur ?
[10:29, 07/12/2023] HIDAYA KH office Num: yes
[11:17, 07/12/2023] Azman HKL: Yesterday discussion with Transformer & Genset supplier.
1. Equipment delivery is in 20/12/2023 by contena.
2. Will use a big heavy crane to lift the Transformer to temporary storage at the 6th floor until the M&E room is cast and ready.
3. Genset will be temporary stor at Ground floor.
4. DCC site PIC will liase with HKL on site coordination so it can be ready during the arrival.
5. DCC will write letters and clear methods of lifting to HKL for record and instruction.