Tuesday, December 5, 2023

06 DEC 2023 HKL

SITE EG MALL 

[09:13, 06/12/2023] Azman HKL: @~Walker Yapi please rectify the bracket as per consultant comments and get approval thru RFI ASAP. πŸ‘†πŸ™

[09:30, 06/12/2023] +60 14-379 2990: Okay man.. πŸ™πŸ»


[13:33, 06/12/2023] Azman HKL: 8th floor. TA1. Request for inspection M&E services. 2pm. @Kadapi J. PROMES . NSC please standby with RFI form. πŸ™
[13:34, 06/12/2023] Kadapi J. PROMES: πŸ‘Œ
[16:50, 06/12/2023] HIDAYA KH office Num: 8th floor. TA1. Request for inspection boss. pipe sleeves installation done just now. @Kadapi J. PROMES


NSC GROUP

[09:41, 06/12/2023] Azman HKL: 8th floor. TA1. M&E inspection in progress. NSC please rectify as per consultant comments.

[10:24, 06/12/2023] Azman HKL: 5th floor. TA2. Slab rebar in progress.\

[10:24, 06/12/2023] Azman HKL: 5th floor. Z6. Lift wall, parapet wall, and, column cast.

[10:24, 06/12/2023] Azman HKL: 3rd floor. Z7. Column rebar in progress

[10:24, 06/12/2023] Azman HKL: 4th floor. Column and scaffolding for 5th floor 8n progress.

[10:24, 06/12/2023] Azman HKL: 2nd floor. TB4. Staircase 3 formwork in progress.
[10:25, 06/12/2023] Azman HKL: @Leung KHπŸ€ @~Walker Yapi please submit RFI and get consultant approval for slab 8th floor, TA1.
[13:21, 06/12/2023] Azman HKL: Please update the daily manpower report. @~Walker Yapi @HIDAYA KH office Num @~.Fazli and progress % @~ShawnChia @Recky Econmech for tomorrow presentation 

[14:33, 06/12/2023] Azman HKL: 8th floor. TA1. M&E services on slab inspection in progress with consultant.

[15:46, 06/12/2023] Azman HKL: Pipe sleeve and duct box up still in progress.



[17:00, 06/12/2023] Azman HKL: 8th floor. TA1. 2nd inspection in progress.
[17:02, 06/12/2023] Azman HKL: Itu semua lepas kerja kasi housekeeping dia. Bekas potong besi, kayu apa saja bekas M&E kerja kasi clear dia. Jangan nanti lain subcon complaint..