[15:27, 04/12/2023] +60 17-866 0355: 3rd floor M&E inspection done
NSC GROUP
[08:53, 04/12/2023] Lo. W. H (HKL-Site Engineer): @HIDAYA KH office Num ada rwdp kah ni?
[08:53, 04/12/2023] Lo. W. H (HKL-Site Engineer): 8th floor sana
[09:40, 04/12/2023] HIDAYA KH office Num: ada hari ni pasang
[09:40, 04/12/2023] Lo. W. H (HKL-Site Engineer): Pasang sudah ambil gambar ya
[09:40, 04/12/2023] HIDAYA KH office Num: okay
[08:53, 04/12/2023] Lo. W. H (HKL-Site Engineer): 8th floor sana
[09:40, 04/12/2023] HIDAYA KH office Num: ada hari ni pasang
[09:40, 04/12/2023] Lo. W. H (HKL-Site Engineer): Pasang sudah ambil gambar ya
[09:40, 04/12/2023] HIDAYA KH office Num: okay
[10:21, 04/12/2023] Raymond Chong. Y. F (HKL P. Manager): Dear all, FYI Tower A Zone 1 (TA/1) 8th floor target casting tomorrow, kindly get ready all conduits by tomorrow 2pm ya