Monday, November 20, 2023

21 NOV 23 HKL

SITE GROUP
EG MALL Azman: 5th floor. Z6. Request for M&E inspection at 2.30pm. @Kadapi J. PROMES . NSC site PIC please stanby and ready RFI form

NSC GROUP

 +60 14-379 2990: Good morning, @EG MALL Azman formwork belum buka.. 

Location : l4th floor n 5th floor staircase 6 wet riser compartment
+60 17-866 0355: @EG MALL Azman @EG MALL Kai @Raymond Chong. Y. F (HKL P. Manager) Ini tatai bata masih belum keras kami boleh potong terus ka? Sebab kalau tidak itu orang sana terus kasi plaster?
EG MALL Kai: No hal, proceed only
EG MALL Kai: Tatai masih ok punya, tapi sudah finish Jgn ko ya
 EG MALL Azman: Saya sda inform Subcon pg bikin. Mana lagi tempat kasi tau aku. Mana boleh pasang pg pasang.
+60 14-379 2990: Okay man. 👍🏻
EG MALL Azman: @~Walker Yapi @~Rimon Joseph 
Tolong kejar semua SPD, LPD kasi siap ya. Mana yang boleh siap inspection. Tolong ya. 🙏🙏
 EG MALL Azman: NSC PIC semua pemasangan yang siap mesti panggil konsultan ya. RFI kasi submit. Mesti ada rekod. Kalau rugi saja pasang tiada rekod. Minta tolong ya. Bos2 semua tolong kasi ingat ya.🙏🙏🙏
EG MALL Azman: Site progress photo.
21/11/2023.
Basement. Z9. Lift pit cast.
EG MALL Azman: 2nd floor. Z7. Ramp slab formwork in progress.
 EG MALL Azman: 5th floor. Z6. Slab rebar and M&E in progress.
 EG MALL Azman: 7th floor. TA2. Slab formwork in progress.
 EG MALL Azman: 4th floor. TB5. Slab formwork in progress.
 EG MALL Azman: 4th floor. TB3. Slab rebar in progress.
 EG MALL Azman: @~Walker Yapi @~Rimon Joseph sedang buka ya. Tolong info kalau ada tempat lain lagi perlu.👆


EG MALL Azman: New Casting Plan
5F - Z6 - 21/11/23 today
4F - TB3 - 22/11/23
2F - Z7(ramp) - 22/11/23
7F - TA/2 - 25/11/23
4F - TB5 - 25/11/23

Please coordinate material, man power and drawing onsite. Date may be changed due to site condition.
EG MALL Azman: BF - Z9B - 30/11/23. Slab target
 Lo. W. H (HKL-Site Engineer): @HIDAYA KH office Num you sudah simpan floor trap kaj
 Lo. W. H (HKL-Site Engineer): ?
 Lo. W. H (HKL-Site Engineer): rwdp
 HIDAYA KH office Num: suda boss
Lo. W. H (HKL-Site Engineer): ok


EG MALL Azman: M&E inspection in progress.
 EG MALL Azman: M&E inspection done. @Mr. Voo @~nas4rie please proceed.
EG MALL Azman: 21/11/23. M&E site walk on site.
EG MALL Azman: @~Walker Yapi please rectify as per comment from consultant.👆
EG MALL Azman: @~Walker Yapi 2nd floor. Please repair as per comment.
 +60 14-379 2990: Noted.
 EG MALL Azman: 1st floor. Sanitary pipe at ceiling level.
 EG MALL Azman: 1st floor. M&E riser room. Request wall to paint.
HIDAYA KH office Num: CW riser room ground floor. can we proceed pipe installation or wait after wall touch up finished? @EG MALL Azman
 EG MALL Azman: Proceed. Just inform me of any obstruction.
 EG MALL Azman: @EG MALL Kai @Raymond Chong. Y. F (HKL P. Manager)  boleh proceed kan.👆
 EG MALL Kai: Internal mcm belum lagi siap bro
EG MALL Azman: Itu plaster dalam pg atas? Ok. Tolong kejar dia. 🙏🙏
 EG MALL Kai: Yea.. tengah kejar dorg
EG MALL Azman: Mereka buat di luar. Tolong minta mereka buat di dalam. 🙏🙏😅
EG MALL Kai: ada sudah saya remind dorg tadi petang jam 1:30
EG MALL Kai: nanti saya comment dorg lagi
 EG MALL Azman: Ok. 💪💪💪. Tq bro
 EG MALL Azman: GF battery room plastering in progress

































 