EG MALL Azman: Good morning.
Site progress photo.
17/11/2023.
7th floor. TA1. Column rebar, lift rebar and slab formwork in progress.
EG MALL Azman: 2nd floor. TB4. Slab formwork in progress.
EG MALL Azman: 5th floor. Z6. Beam rebar in progress.
EG MALL Azman: 3rd floor. TB5. Column rebar in progress
] +60 10-941 8970: @EG MALL Azman PLS double check for M&E materials need to install at column 7F zone TA1 2F zone 7 3F zone TB5 C&S columns formwork in progress already 🤝🙏🏻💪🏻
+60 17-866 0355: sudah pasang nas siap sudah
60 17-866 0355: 👍
EG MALL Azman: Ok Nas. @~Leppong tolong yer. 🙏
+60 14-379 2990: @EG MALL Azman @~nas4rie kindly request for formwork removal support from maincon.. tq
+60 12-843 3877: Wiring@Level 3&4
EG MALL Azman: Ok. Sudah saya inform Subcon. Mungkin hari ni atau bsok mereka start buka. Tolong inform sini yeh kalau belum buka. Kita try💪💪
+60 14-379 2990: Okay man.. thanks
EG MALL Azman: Tolong tgk itu di basement. Itu column kalau sda kena skim.🙏🙏🙏
+60 14-379 2990: 4 nos column ready sdah.
EG MALL Azman: Ini lagi bah kan.. 😅
+60 14-379 2990: In progress tu.