Sunday, November 12, 2023

13 NOV 23 HKL

SITE GROUP
 EG MALL Azman: Request for inspection M&E services at 3pm. 3rd floor. TB5. @Kadapi J. PROMES . NSC please stand by on site early. TQ.
Kadapi J. PROMES: 👌


 EG MALL Azman: M&E inspection in progress.

 EG MALL Azman: Done M&E inspection. Please proceed.



NSC GROUP
 EG MALL Azman: Monday safety tool box for NSC at ground floor.
EG MALL Azman: Site progress photo.             13/11/2023.                                          3rd floor. TB5. Slab rebar and M&E in progress
EG MALL Azman: 2nd floor. Z6. Slab formwork in progress
EG MALL Azman: 1st floor. TB4. Slab formwork and rebar in progress.
Lo. W. H (HKL-Site Engineer): @HIDAYA KH office Num

 Lo. W. H (HKL-Site Engineer): ada tu flow trap kamu x ?
Lo. W. H (HKL-Site Engineer): kalau ada pasang ....
Lo. W. H (HKL-Site Engineer): @Leung KH🍀
EG MALL Azman: @~Walker Yapi ini hose reel drop dari 4th floor bah kan.
 EG MALL Azman: M&E inspection in progress.
EG MALL Azman: Done M&E inspection. @Mr. Voo @~nas4rie please proceed.

















 