Thursday, November 9, 2023

10 NOV 23 HKL

SITE GROUP
EG MALL Azman: 6th floor. TA2. Request for M&E inspection at 10am by today..@Kadapi J. PROMES

NSC GROUP
 EG MALL Azman: Good morning.
Site progress photo.
10/11/2023.
7th floor. TA1. Slab rebar and M&E in progress
 EG MALL Azman: 6th floor. TA2. Rebar and M&E in progress.
EG MALL Azman: 6th floor. TA1. Rebar and M&E in progress.
EG MALL Azman: 3rd floor. TB5. Slab formwork in progress.
EG MALL Azman: 4th floor. Z6. Lift wall rebar and 5th floor slab rebar in progress.
 EG MALL Azman: 2nd floor. Z7. Slab formwork in progress.
EG MALL Azman: @~Walker Yapi tolong atur πŸ‘†. Itu SPD punya collar kalau ada, kasi pasang dia sebelum kena tutup bata.
EG MALL Azman: Kalau ada sebab tidak dapat sambung tolong inform ya supaya kerja boleh jalan.
 Dart Econmech: Smpai sdh collar d site. Jadi dorg terus pasang jg ari ni πŸ™πŸΏ

EG MALL Azman: 6th floor. TA2. Request for M&E inspection at 10am by today..@Kadapi J. PROMES
HIDAYA KH office Num: morning. belum lagi kena kasi bersih ni. πŸ™πŸΌ @EG MALL Azman
 +60 14-379 2990: Collar ada sudah @EG MALL Azman nnti kami pasang . Str 9 & str 5
 EG MALL Azman: @EG MALL Kai tolong dulu orang susah.. πŸ™πŸ™πŸ™πŸ₯²
EG MALL Kai: Aiyoo.. dorg ni ah.. orz
EG MALL Kai: Kejap saya call dorg
 HIDAYA KH office Num: hari ni mau jalan sana suda dalam jam 1
EG MALL Azman: @~Walker Yapi stanby RFI kita panggil konsultant inspect mana yang sda ready ya. πŸ™πŸ’ͺπŸ’ͺ
Jimmy HKL: @~Walker Yapi bagi kerjasama sekiranya ada lubang mcm nie tolong tutup balik coz bahaya jatuh.
 +60 19-809 6068: Okay, nanti kami tutup.
 HIDAYA KH office Num: Masih belum clear boss πŸ™πŸΌπŸ™πŸΌ @EG MALL Kai
 EG MALL Kai: πŸ˜₯ steady ko, saya pigi tegur dorg lagi πŸ™πŸ»
Jimmy HKL: saya dah tutup so tolong peka bahaya mcm ini dan sekiranya berulang saman akan menyusul.
 +60 14-379 2990: Noted  with action.. thanks @Jimmy HKL
 +60 19-809 6068: M&E inspection in progress 6th floor
 HIDAYA KH office Num: @EG MALL Azman when you can start the finishing works for the water tank plinth at 3rd floor?
 Lo. W. H (HKL-Site Engineer): archi latest basement to 7th mezz floor
Lo. W. H (HKL-Site Engineer): Dear valued NSC, this is the latest archi drawing in cad file, please vet through ..should you find discrepancy vs your scope please highlight immediately
EG MALL Azman: @EG MALL Kai ini tolong juga ya atur subcon. Top level plinth finishing. Sini duluan. Lepas tu basement zone 5, and basement fire tank area. πŸ™πŸ™πŸ™
 EG MALL Kai: Ok bah, tapi sekrg saya punya ada low in stock.. kena tunggu dulu ya πŸ™πŸ»πŸ™πŸ»
 EG MALL Azman: 6th floor. TA2. Done inspection. @Mr. Voo @~nas4rie please procerd.
Mr. Voo: πŸ‘πŸ»



































 