Sunday, October 29, 2023

30 OCT 23 HKL

SITE GROUP
EG MALL Azman: 1st floor. Z7. Request for inspection M&E.  4pm. @Kadapi J. PROMES


NSC GROUP

EG MALL Azman: Morning. Safety toolbox 9.00am. All NSC site workers please attend. TQ.
 HIDAYA KH office Num: okay
EG MALL Azman: Housing for water pump plinth at basement fire tank room
EG MALL Azman: @~Walker Yapi 👆
EG MALL Azman: Ground floor. NSC safety tool box. 9.00am.
 EG MALL Azman: Site progress photo. 
30/10/2023.
1st floor. Z7. Slab rebar and M&E services in progress.
EG MALL Azman: 1st floor. TB4a. Slab formwork in progress.
 EG MALL Azman: 2nd floor. TB5. Column rebar in progress
EG MALL Azman: 5th floor. TA2. Skab formwork and rebar in progress.
 EG MALL Azman: TA2. 5th floor. Slab formwork and rebar in progress
 EG MALL Azman: 7th floor. TA1. Slab beam formwork in progress.
EG MALL Azman: Basement. Z9. Earthwork in progress
 EG MALL Azman: Basement earthwork in progress
 EG MALL Azman: @~Walker Yapi morning. Kamu punya subcon ducting ada datang ini hari kan? Kasi report awal ya. Mana kamu start. Itu SPD riser.
[09:46, 30/10/2023] +60 14-379 2990: Okay man.
EG MALL Azman: Sedang kasi bersih. @~Walker Yapi nanti petang kita tgk. Pg marking dia.👆
+60 14-379 2990: Marking plinth fire pump siap sudah .. @~Nasri @EG MALL Azman
 EG MALL Azman: M&E services inspection in progress
EG MALL Azman: Done M&E inspection. @Mr. Voo @~Nasri please proceed.




























 