SITE GROUP
EG MALL Azman: 4th floor. TA2. Request for inspection of M&E services. 10am.  @Kadapi J. PROMES 🙏

NSC GROUP
EG MALL Azman: NSC tool box hari ini 9am. Semua NSC di tapak mesti hadir ya.
 EG MALL Azman: 4th floor. TA2. Slab ready for inspection.
EG MALL Azman: 2nd floor. TB3. Slab rebar and M&E in progress.
 EG MALL Azman: 1st floor. TB4. Slab formwork and support scaffolding in progress.
 EG MALL Azman: 2nd floor. TB5. Slab formwork in progress.
 EG MALL Azman: 1st floor. Z8. Column rebar and slab beam formwork in progress.
 EG MALL Azman: 6th floor. TA1. Lift wall rebar in progress.
 EG MALL Azman: 6th floor. Z4. Column rebar in progress.
EG MALL Azman: Basement. Z9. Slab foundation in progress.
EG MALL Azman: Tool box, NSC.. 9am.


 EG MALL Azman: 4th floor. TA2. M&E services inspection. Done. @~Nasri @Mr. Voo please proceed.
EG MALL Azman: 2nd floor. TB5. Slab formwork and rebar in progress
 EG MALL Azman: 2nd floor. TB3. Slab rebar and M&E service in progress.
+60 12-843 3877: Installation PVC conduit in progress@level 2































 