EG MALL Azman: Morning. For info, Genset installer informs me yesterday that they will come in tomorrow. Friday.
Dart Econmech: Man esok jangan lupa
EG MALL Azman: Ini. π. Baru maw lupa. π
Dart Econmech: Ya tq ππΏπ€£
EG MALL Azman: Site progress photo.
19/10/23.
Ground floor. Z8. Slab rebar and M&E in progress.
EG MALL Azman: 2nd floor. TB5. Slab formwork in progress.
EG MALL Azman: 4th floor. Slab formwork and beam rebar in progress.
EG MALL Azman: Basement. Z9. Earthwork in progress.
EG MALL Azman: 2nd floor. TB3. Slab formwork in progress.
EG MALL Azman: Ground floor. TB4a. Slab rebar and M&E in progress.
EG MALL Azman: 4th floor. Sprinkler pipe in progress.
EG MALL Azman: 4th floor. Cable trunking in progress.
EG MALL Azman: 4th floor. Cable pulling in progress.
Mr. Voo: @EG MALL Azman
Mr. Voo: Mo extend kah ?
Raymond Chong. Y. F (HKL P. Manager): mesti ba
EG MALL Azman: @HIDAYA KH office Num tolong pg sana ground floor. Tgk ini pipe..ππ
HIDAYA KH office Num: Okay2
EG MALL Azman: 3rd floor. Cable & trunking in progress.
EG MALL Azman: 1st floor. Sanitary pipe and tie rod installation for 2nd floor services in progress.
EG MALL Azman: Ground floor. Sanitary pipe and cable trunking are in progress.