NSC GROUP
EG MALL Azman: Hi morning @Dart Econmech . As we discussed yesterday on site, please ask your chiller subcon to come ASAP and confirm on how to transport the Chiller to the basement.
Dart Econmech: Good morning. yes we have 2 option. tmorrow morning we set up the meet up and discussion.
EG MALL Azman: @Raymond Chong. Y. F (HKL P. Manager) @Mr. Voo please take note. As per discuss with econmech, only tomorrow their specialist comes to confirm us. So I do not want to hold any urgent progress on site until NSC discusses and confirms us their planning. @Dart Econmech please chase your specialist. Thanks. 🙏🙏🙏
EG MALL Azman: Site progress photo.
12/10/23.
1st floor. TB5. Slab cast.
EG MALL Azman: 3rd floor. TA2. Slab rebar and M&E services installation in progress.
EG MALL Azman: 6th floor. TA1. Slab formwork in progress
EG MALL Azman: Ground floor, TB4. Slab formwork in progress
EG MALL Azman: Ground floor. Z6. Slab formwork in progress
Raymond Chong. Y. F (HKL P. Manager): if they are late then they have to think of their own way where to bring in the chillers
Raymond Chong. Y. F (HKL P. Manager): We will just provide them the space, they need to bring it down their ways
Dart Econmech: Space too far from the landing. Mobile crane cant swing it to here.
Dart Econmech: Tomorrow will confirm back to your side.
Raymond Chong. Y. F (HKL P. Manager): need not to confirm back, we have already provide the space for u, u have to think of ur solutions
+60 17-866 0355: LV 3 pasang Trang king