Wednesday, October 11, 2023

11 OCT 23 HKL

NSC GROUP
EG MALL Azman: Site progress photo.
11/10/23.
1st floor. TB5. Slab rebar in progress.
 EG MALL Azman: 3rd floor. TA2. Beam rebar in progress
EG MALL Azman: Ground floor. 5b. Slab beam formwork in progress.
 EG MALL Azman: @HIDAYA KH office Num 👆cek ya pipe sleeve. Nanti Afat bising.
 HIDAYA KH office Num: Okay
 EG MALL Azman: @~Walker Yapi @~Rimon Joseph daily man power? Kelmarin? Daily please...🙏🙏🙏🤯
 +60 17-866 0355: M&E inspection
Dart Econmech: Good Day Mr @Raymond Chong. Y. F (HKL P. Manager) Our chiller will be deliver soon. Can we hv small discussion regarding the chiller placement and storage?
 Raymond Chong. Y. F (HKL P. Manager): sure, please meet up today 3pm
 Dart Econmech: Ok thanks 🙏🏿
+60 10-941 8970: @EG MALL Azman cable kamu tolong atur macam mana ni?
EG MALL Azman: @~Leppong kasi naik dia..
EG MALL Azman: @~LO KEAM any new info from your subcon? Please arrange. 🙏🙏
 +60 19-895 9900: 👌🏻👌🏻👌🏻
Raymond Chong. Y. F (HKL P. Manager): @EG MALL Azman any updates for the Genset specialist coming?
EG MALL Azman: Genset Subcon call me and inform by next week thursday.
Raymond Chong. Y. F (HKL P. Manager): Make sure don’t postpone again
 Dart Econmech: After finish with promes i come meet u mr raymond. Just now still at promes
Raymond Chong. Y. F (HKL P. Manager): @EG MALL Azman please join
 EG MALL Azman: Ok will join after done inspection.
EG MALL Azman: 1st floor. TB5. M&E slab services inspection done. @Mr. Voo @~Nasri please proceed.

















 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...