Monday, October 9, 2023

09 OCT 23 HKL

NSC GROUP
Lo. W. H (HKL-Site Engineer): @HIDAYA KH office Num this is the pipe that you need to extent …. … ground floor area is on the green edge … prior drain
HIDAYA KH office Num: Okay
Lo. W. H (HKL-Site Engineer): Asap ya thanks
HIDAYA KH office Num: Okay boss boleh
 Lo. W. H (HKL-Site Engineer): 👍
EG MALL Azman: Site progress photo.
9/10/23.
3rd floor. TB3. Slab rebar and M&E in progress.
EG MALL Azman: 1st floor. TB5. Slab rebar and M&E in progress
EG MALL Azman: 3rd floor. TA2. Slab rebar and M&E in progress.
EG MALL Azman: Basement. 5b. Slab rebar in progress
EG MALL Azman: Ground floor. Earthwork in progress.
EG MALL Azman: 1st floor. TB3. Slab RFI 2.30pm. @HIDAYA KH office Num @~.Fazli @~Walker Yapi please stanby.  Tq.
HIDAYA KH office Num: Okay
+60 14-379 2990: M&E inspection done
 EG MALL Azman: 1st floor. TB3. M&E inspection done. @~Nasri @Mr. Voo please proceed.















 