Friday, October 6, 2023

06 OCT 23 HKL

NSC GROUP

 EG MALL Azman: 1st floor. TB3. Slab formwork and beam rebar in progress.
EG MALL Azman: 2nd floor. TA2. Slab formwork in progress
 EG MALL Azman: 1st floor. TB5. Slab formwork and M&E services in progress
EG MALL Azman: 6th floor. TA1. Slab formwork in progress
EG MALL Azman: Basement, 5b. Retaining wall cast.









 

No comments:

Post a Comment

  EGMALL COORDINATION (6 18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation. 18th floor. Tow...