SITE GROUP
60 12-843 3877: Level 4_wiring in prograss
+60 12-843 3877: ๐ค๐ปLevel 3_correction
+60 12-843 3877: Slab_Level 5.PVC conduit in rectification
NSC GROUP
EG MALL Azman: Morning @~LO KEAM please inform your Genset subcon to confirm when they start mobilized the equipment in genset room. Thanks. ๐๐
+60 19-895 9900: Ok, dalam bilik sdh siap?
EG MALL Azman: Site progress photo.
4/10/2023.
5th floor. TA2. Slab rebar and M&E in progres
EG MALL Azman: Basement. Z5b. Retaining wall formwork closure in progress
EG MALL Azman: 6th floor. TA1. Slab formwork in progress
EG MALL Azman: 3rd floor. TA2. Scaffolding support and column in progress.
EG MALL Azman: 1st floor. TB3. Slab formwork and beam rebar in progress.
EG MALL Azman: 1st floor. TB5. Slab formwork in progress
EG MALL Azman: Plastering siap. Tinggal itu bata di tank dan floor screeding. Last skali painting.
+60 19-895 9900: Ok, sya atur
EG MALL Azman: TQ๐๐ป
EG MALL Azman: Basement. 4b. Retaining wall formwork closure in progress. @HIDAYA KH office Num cek any pipe sleeve thru wall to install. ๐
+60 16-526 1788: Cepat
+60 16-526 1788: Tolong cepat
HIDAYA KH office Num: In progress
+60 12-843 3877: Level 4_wiring in prograss
+60 12-843 3877: ๐ค๐ปLevel3 pembetulan
+60 12-843 3877: Slab_Level 5.PVC conduit in rectification
+60 12-843 3877: 04/10/23
EG MALL Azman: 1st floor. TB5. Slab rebar in progress.
EG MALL Azman: 5th floor. TB2. M&E inspection done. @~Nasri @Mr. Voo please proceed.
EG MALL Azman: Basement. 4b. Joint inspection pipe sleeve outlet .