Tuesday, October 31, 2023

01 NOV 23 HKL

SITE GROUP
EG MALL Azman: SPD fabrication and installation in progress at 1st floor. ST5, ST8.👆@Kadapi J. PROMES
EG MALL Azman: Mitsubishi on site to check the casted lift perimeter.

NSC GROUP
]EG MALL Azman: Site progress photo.
1/11/23.
1st floor. Slab beam rebar in progress.
EG MALL Azman: 1st floor, TB4. Column rebar in progress
 EG MALL Azman: 1st floor. Column rebar in progress
EG MALL Azman: 2nd floor. Column rebar in progress
EG MALL Azman: Basement. Z9. Earthwork and slab foundation in progress.
EG MALL Azman: 7th floor. Slab beam formwork in progress.
EG MALL Azman: @~Rimon Joseph ini semua ducting SPD kan. Itu ST9, ST7, ST5 tolong cek dia boleh pasang k. Bila start pasang panggil saya k. Kita bawa konsultan. Kalau ada masalah inform saya.🙏
EG MALL Azman: 1st floor. Z7. Column rebar in progress.
+60 19-809 6068: SPD fabrication and install in progress 1st floor..
+60 16-526 1788: 🤲🏾
EG MALL Azman: @~LO KEAM Any new update regarding this item?
Edwin Chen 013: @Lo. W. H (HKL-Site Engineer), any update on our submission for the scupper drain SD?
 Lo. W. H (HKL-Site Engineer): I yet received any
+60 19-895 9900: Apa item?
Lo. W. H (HKL-Site Engineer): item a and item b,c
EG MALL Azman: Weight of each equipment for slab design purposes.
 +60 19-895 9900: Bukan dah submit kah?
 +60 19-895 9900: Pls check email & ur counter
 +60 19-895 9900: Item b&c we awaiting latest elec construction dwgs only we can provide
 +60 19-895 9900: Hope its clarified tq
EG MALL Azman: TQ bro. 👌 tdk perasan bah. 👍🏻👍🏻
+60 19-895 9900: 😄👍🏻👍🏻👍🏻

 EG MALL Azman: 👍🏻
+60 14-379 2990: Staircase 5 Level 1
+60 14-379 2990: Staircase 5 Level 2
+60 14-379 2990: Staircase 5 Level 3
 +60 14-379 2990: Progress pressurisation duct @EG MALL Azman































 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...