SITE GROUP
EG MALL Azman: 2nd floor. TA2. Request for inspection at 2.30pm. @Kadapi J. PROMES .
EG MALL Azman: 5th floor. TA1. Lift wall opening. Mitsubishi on site to inspect the lift wall opening.
NSC GROUP
EG MALL Azman: @EG Mall Kin Hong Site Coord Chong SY @EG Mall Plumber Leung WK - King Hong morning. Tolong atur tutup ini pipe. Maw timbun ini tanah skrg.
[08:29, 29/09/2023] EG MALL Azman: @HIDAYA KH office Num
HIDAYA KH office Num: Okay2 boleh
EG MALL Azman: Site progress photo.
29/09/2023.
2nd floor. TA2. Slab rebar and M&E in progress.
EG MALL Azman: 1st floor. TB3. Slab formwork and scaffolding support inprogress.
EG MALL Azman: Ground floor. TB4. Column formwork in progress.
EG MALL Azman: Ground floor. TB5. Slab formwork and support scaffolding in progress.
EG MALL Azman: Basement. Z5b. Retaining wall formwork closure and slab formwork in progress
+60 12-843 3877: 2nd floor_conduit in progress
+60 12-843 3877: 3rd floor-Wiring in prog
EG MALL Azman: 4th floor. z6. lift formwork and parapet wall..
Dart Econmech: @EG MALL Azman pls improve yr mosquito control on site. My site at elemen was given notice 1 week close due to mosquito and water stagnant. 🙏🏿
EG MALL Azman: Thanks for advise. @Jimmy HKL .. 👆. 🙏🙏🙏
Dart Econmech: Welcome. 🙏🏿
Jimmy HKL: noted will improve. tq
EG MALL Azman: Mobile scaffolding training. Erecting training.
EG MALL Azman: 2nd floor. Zone TA2. M&E services inspection done. @Mr. Voo @~Nasri please proceed. 👌