+60 12-843 3877: Installation G_I conduit_water tank Besment-done
Kadapi J. PROMES: 👍👌
NSC GROUP
EG MALL Azman: Good morning.
Site progress photo.
27/09/2023. 5th floor. TA1. Slab casted.
EG MALL Azman: 4th floor. TB2. 5th floor support scaffolding and beam formwork in progress.
EGLL Azman: 2nd floor. TA2. Slab formwork and beam rebar inpogress.
EG MALL Azman: 1st floor. TB3. Slab formwork and support scaffolding in progress.
EG MALL Azman: Basement. 5b. Retaining wall rebar and slab rebar in progress. Watertank plinth casted.
EG MALL Azman: 4th floor. Z6. Parapet wall rebar and lift formwork.
EG MALL Azman: 1st floor. TB5. Slab/beam formwork in progress.
EG MALL Azman: Daily Man power, please share some activity photo. TQ. 🙏🙏.
EG MALL Azman: @~Walker Yapi @~Rimon Joseph cepat kejar ini. Hari ini mesti buat. Bsok maw tgk ini siap.
EG MALL Azman: Ini lagi. Buat ini hari bsok maw dia siap.
EG MALL Azman: 3rd floor. Wiring cable in progress.
EG MALL Azman: Site meeting today.. 👆
Dart Econmech: Ok noted
EG MALL Azman: Meeting start now.
+60 12-843 3877: Level besment&3rd flr
EG MALL Azman: @~Walker Yapi Get me some activity photo.
EG MALL Azman: @~Walker Yapi tiada bikin wall ini hari? Bila boleh bikin?
EG MALL Azman: @~LO KEAM confirm ya. By next week genset subcon is coming to the site. We are planning work on floor screeding to complete the room. 🙏
] +60 19-895 9900: Now they r going bro, otw
+60 14-379 2990: Bagi kami masa sampai hari jumaat? Boleh..
EG MALL Azman: Ok. Jumaat ya.. nanti kasi plaster cantik.
EG MALL Azman: Ok. Noted.