SITE GROUP
EG MALL Azman: 5th floor, TA1. M&E services inspection in progress. @~Leppong @HIDAYA KH office Num standby at 5th floor.
HIDAYA KH office Num: Okay
EG MALL Azman: DCC installing lighting points in progress.
EG MALL Azman: Electrical services inspection in progress..
EG MALL Azman: 5th floor. TA1. Done M&E inspection. @~Nasri @Mr. Voo please proceed. 👌
NSC GROUP
EG MALL Azman: @~Walker Yapi @~Rimon Joseph check your break glass conduit at ST3, Basement.
EG MALL Azman: Good morning.
Site progress photo.
26/09/23.
4th floor. TB2. Slab cast.
EG MALL Azman: 5th floor. TA1. Slab rebar and M&E in progress.
EG MALL Azman: 4th floor. Z6. Parapet wall, lift formwork.
EG MALL Azman: 2nd floor. TA2. Slab formwork in progress
EG MALL Azman: 1st floor. TB3. Slab formwork and scaffolding support in progress.
EG MALL Azman: Ground floor. TB4. Column formwork in progress.
EG MALL Azman: Basement. Z4b. Slab foundation cleaning in progress.
EG MALL Azman: Basement. 5b. Water tank plinth formwork in progress.
+60 14-379 2990: @EG MALL Azman , sini ada brick wall ka? Bawah beam..
EG MALL Azman: @~Walker Yapi @~Rimon Joseph uneven surface plastering. Ini kalau finishing nanti akan nampak. Kasi rata dia guna kertas pasir. Kalau ada crack plaster balik kasi rata dia. Buat segera ya. @Dart Econmech tolong ya. 🙏🙏🙏
EG MALL Azman: Ada brick wall.. ini break glass bah kan. Cek itu position. Tembus itu lantai. Cek macam mana DCC pasang dia punya conduit.
EG MALL Azman: Itu pintu punya tempat. Cek sana site..
EG MALL Azman: 4th floor. Sprinkler pipe installation in progress..
EG MALL Azman: NSC kalau ada pipe sleeve di slab, kasi tutup dia begini atau sumbat pakai kertas di dalam. 🙏🙏 cuba kasi kurang sumbat semasa konkrit.
EG MALL Azman: @~Rimon Joseph @~Walker Yapi daily manpower?🙏🙏