 EG MALL Azman: Site photo progress.
23/09/23.
Ground floor. TA3/a. Slab work in progress.
 EG MALL Azman: Ground floor. TB5. Slab work in progress.
EG MALL Azman: 5th floor. Zone TA1. Slab formwork in progress.
EG MALL Azman: Ground floor. TA3/TA4. Column rebar and formwork in progress.
+60 12-843 3877: Installation PVC cable Level-4
 EG MALL Azman: Ground floor. TB. M&E services inspection in progress..
EG MALL Azman: Inspection electrical conduit in progress..

 EG MALL Azman: Ground floor. TB5 & TB3-a. M&E inspection done. @~Nasri @Mr. Voo please proceed. 👌













 