Monday, September 18, 2023

18 SEP 23 HKL

NSC GROUP
EG MALL Azman: Good morning. 
18/9/23.
Site progress photo.
1st floor. Ta2. Slab rebar.
EG MALL Azman: TB2. 3rd floor, Column rebar in progress. 4th floor, beam formwork and scaffolding.
EG MALL Azman: 5th floor. TA1. Slab formwork in progress.
EG MALL Azman: Z4. 6th floor. Slab formwork in progress
 EG MALL Azman: Z5. 6th floor. Lift wall formwork in progress.
 EG MALL Azman: Z4. Basement. Slab foundation rebar in progress
EG MALL Azman: Ground floor. TB3/TB4. Column rebar in progress.
EG MALL Azman: TB5. Basement. Slab rebar inprogress.
EG MALL Azman: Basement earthwork in progress
EG MALL Azman: 4th floor. Z6. Lift wall formwork and parapet wall rebar in progress.
+60 12-843 3877: Installation PVC cable for lightings.Level 4
EG MALL Azman: Hi @Dart Econmech please push your subcon start install Sprinkler pipe by this week, if no obstruction. 🙏🙏🙏💪.
 Dart Econmech: Ok noted























 