SITE GROUP
EG MALL Azman: Good morning.
Site progress photo.
12/09/23.
4th floor. TA1. Slab cast.
EG MALL Azman: 4th floor. Z6. Slab rebar and M&E.
Raymond Chong. Y. F (HKL P. Manager): This slab casting today
EG MALL Azman: 3rd floor. TB2. Slab rebar in progress.
Raymond Chong. Y. F (HKL P. Manager): This slab casting 14/09/23
Raymond Chong. Y. F (HKL P. Manager): This one bring forward today
Raymond Chong. Y. F (HKL P. Manager): TB/2 3rd floor slab casting today
Raymond Chong. Y. F (HKL P. Manager): @EG MALL Azman TB/2 3rd floor also casting today ya
EG MALL Azman: Noted. If bottom rebar can be completed before 12 we can throw all the men here after lunch.
EG MALL Azman: Basement. Z4/a Retaining wall. Formwork done.
EG MALL Azman: 1st floor. TA2. Beam rebar in progress.
Raymond Chong. Y. F (HKL P. Manager): This slab casting 14/09/23
EG MALL Azman: Ground floor. TB3/TB4. Slab rebar and M&E in progress.
Raymond Chong. Y. F (HKL P. Manager): this slab casting 13/09/23
EG MALL Azman: 7th floor. Z4. Slab formwork and scaffolding in progress.
EG MALL Azman: 6th floor. Z5. Column rebar in progress. Lift rebar in progress.
EG MALL Azman: 6th floor. TB1. Column rebar in progress.
EG MALL Azman: Morning. We request for inspection. 4th floor. Zone 6. Slab M&E inspection at 9.00am. @Kadapi J. PROMES
EG MALL Azman: M&E in progress.
EG MALL Azman: Sorry to inform you that today there should be an M&E site walk. So site PIC get ready a site walk with consultant at 4pm. Thank you. There is no site meeting. 🙏
EG MALL Azman: Please bring any latest drawing to discuss.. if any.
EG MALL Azman: @Kadapi J. EG Mall Promess Gadapi 3rd floor. Zone TB2. Request stanby on site for M&E inspection after M&E services done installation. @~Leppong @~Walker Yapi please stanby to complete the M&E. Casting plan by today..
Kadapi J. PROMES: Conferm kah? Formwork belum siap owhh. Jam berapa mau cast?
Kadapi J. PROMES: @Raymond Chong. Y. F (HKL P. Manager)
Kadapi J. PROMES: ?
Raymond Chong. Y. F (HKL P. Manager): Ini malam cast
Raymond Chong. Y. F (HKL P. Manager): Tunggu batching plant confirm masa
Kadapi J. PROMES: Ok saya tunggu
Kadapi J. PROMES: Kita tunggu siap lorrr.
Kadapi J. PROMES: Sikit jam lagi ni
+60 12-833 6147: 😅👍🏻
+60 17-866 0355: M&E inspection done
NSC GROUP
+60 17-866 0355: Asman hari ini mau tuang.ka ni tempat
EG MALL Azman: Iya.. maw kejar tuang ni hari..
EG MALL Azman: @HIDAYA KH office Num tolong cek ni paip. Air ada masuk lagi agak banyak.
HIDAYA KH office Num: Okay saya cek
EG MALL Azman: 4th floor. Z6. M&E inspection in progress.
EG MALL Azman: M&E inspection done with some minor damage to repair. Repair work in progress.
EG MALL Azman: M&E inspection done. @Mr. Voo please proceed.. 👌
Mr. Voo: 👍🏻
EG MALL Azman: @~Walker Yapi @Leung KH🍀 please check the dropper pipe sleeve floor trap and hose reel. 1st floor, ST9 area. It should be inside the hose reel room. 🙏
Edwin Chen 013: @HIDAYA KH office Num , please check
+60 14-379 2990: Ok Man. Will check
HIDAYA KH office Num: Okay
EG MALL Azman: M&E coordination meeting today. 4.00pm after the subcon weekly meeting.
EG MALL Azman: Sorry to inform you that today there should be an M&E site walk. So site PIC get ready a site walk with consultant at 4pm. Thank you. There is no site meeting. 🙏
+60 17-866 0355: Azman tunggu besi siap baru boleh pasang conduit
EG MALL Azman: OK.
60 17-866 0355: bos sampai sekarang M&E belum boleh masuk
+60 10-941 8970: Inspection electrical and elv conduit
+60 17-866 0355: M&E inspection done
No comments: