EG MALL Azman: Site progress photo.
8/9/23.
4th floor. TA1. Slab ebar n M&E in progress.
EG MALL Azman: 4th floor. Z6. Slab rebar in progress
EG MALL Azman: Ground floor. TB3/TB4. Slab rebar in progress.
EG MALL Azman: 3rd floor. Slab/beam formwork in progress
EG MALL Azman: 1st floor. TA2. Slab formwork& scaffolding in progress. Basement Z4a cast.
EG MALL Azman: 9 pallet fire water tank store in the basement.
EG MALL Azman: @~Walker Yapi boleh keluar ini kontena ini hari ka? Pasang balik itu barrier. Kalau ada sampah kasi bersih.
+60 14-379 2990: Barrier sudah pasang balik... saya usahakan malam ini collect ini container.. 🙏🏻
EG MALL Azman: Boleh ambil dari sini kalau tdk cukup.