Wednesday, September 6, 2023

07 SEP 23 HKL

NSC GROUP

 EG MALL Azman: Good morning..
Site progress photo.
7/9/23.
4th floor. Zone TA1. Slab rebar and M&E in progress.
 EG MALL Azman: 6th floor. Zone 4. Slab formwork in progress.
EG MALL Azman: 6th floor. Zone 5. Column rebar in progress
EG MALL Azman: 6th floor. TB1. Column
EG MALL Azman: 4th floor. Zone 6. Slab formwork and beam rebar in progress.
 EG MALL Azman: 3rd floor. Beam/slab formwork and scaffolding in progress
 EG MALL Azman: Basemen. Zone 4a. Slab foundation rebar in progress.
 EG MALL Azman: 1st floor. TA2. Slab formwork in progress.
EG MALL Azman: Ground floor. TB3/TB4. Slab rebar in progress.
EG MALL Azman: @Dart Econmech @~Walker Yapi as we discuss, 3rd floor, you can start install the tie rod for sprinkler main pipe before your fitting arrival. Please check and inform me of any problems to start. Please!!
Dart Econmech: We are arranging. 🙏🏿
Dart Econmech: We will start soon. Est nextweek my fittings arrive. The team will mobilize after the fitting delivered on site.
[09:20, 07/09/2023] EG MALL Azman: Thanks, 🙏.

EG MALL Azman: @Dart Econmech @Recky Econmech please double check 3rd floor coordination drawing. Some  changes to the chiller pipe (clouded area) and sprinkler main pipe. Inform me if any problem. Thanks.
Recky Econmech: Sprinkler pipe should be no problem,



















 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...