Tuesday, September 5, 2023

06 SEP 23 HKL

SITE GROUP
EG MALL Azman: Good morning. 
Site photo progress.
6/9/23.
4th floor. TA1. Slab rebar & M&E in progress.


 EG MALL Azman: 6th floor. Z4. Slab formwork.
EG MALL Azman: 6th floor. Z5. Column rebar in progress.
EG MALL Azman:  6th floor. TB1.
EG MALL Azman: Ground floor. TB3/TB4. Slab rebar in progress
 EG MALL Azman: 1st floor. TA2. L shape. Slab formwork and scaffolding in progress.
EG MALL Azman: Basement. Zone 5. Earthwork bore pile in progress


NSC GROUP

EG MALL Azman: @Leung KH🍀 bro. Kalau ada free itu TC2 kasi atur saja angkat itu panel ya sama itu signalman. Itu kawasan maw korek.
Leung KH🍀: Morning bro , tiada masalah 🙏🏻 Minta TC2 kasih atur saja sebab kemarin orang saya tunggu sana saja satu hari tapi TC2 sibuk angkat barang lain 🙏🏻 Tqtq
EG MALL Azman: Iya bro. Minta atur sama itu signalman saja awal pagi. Set masa saja bila dia free. Jangan tunggu kalau dia sibuk. 😅
EG MALL Azman: Boleh guna ini platform sini 3rd floor.

EG MALL Azman: @~Leppong 1st floor. ST5. Tolong check ini conduit apa masalah dia. Itu simen tidak dapat masuk kerana itu konduit ka? Cek dia kasi kompom betul2..
[10:11, 06/09/2023] +60 17-866 0355: ok kami cek  dulu
+60 17-866 0355: @EG MALL Azman apa masalah conduit ini. Ini sebab kurang simen kurang vibrate. Tempat lain pasang sama begini juga tiada lobang begini. Ini sebab kurang vibrate simen.

 Dart Econmech: Our tank also arrived. 2 nos 40ft container.
Dart Econmech: @Raymond Chong. Y. F (HKL P. Manager) @EG MALL Azman 🙏🏿
 EG MALL Azman: Dart, confirm date, apa material sampai, tempat maw simpan.
Dart Econmech: Hdg pressed tank for spk, wet riser and hr tank

7-8 sept 2023

2 nos 40ft container

Place at basement
Raymond Chong. Y. F (HKL P. Manager): we have already 2 containers at site, will only be cleared by 9th Sept. can postpone your delivery?
 Dart Econmech: Until 10th mr raymond?
Raymond Chong. Y. F (HKL P. Manager): about that
Dart Econmech: GL 7-8 / J-K basement. Can we place here?
EG MALL Azman: @Dart Econmech Maw parking kontena 40' disini kan.
 Dart Econmech: Thanks
Dart Econmech: 🙏🏿




EG MALL Azman: New casting plan update
 🌂=Changes
Zone 4/a- B flr-🌂7/9/23
Zone 6 - 4th flr - 🌂 8/9/23
Zone 9/a - ret. Wall. - 8/9/23
Zone TA1-4th flr-🌂9/9/23
Zone TB/2- 3rd floor-10/9/23
ZoneTA/2-1st flr-🌂12/9/23
Zone TB/3 - GF - 🌂15/9/23
Zone TB/4 - GF - 🌂15/9/23
Zone 4 - 7th floor - 12/9/23

Hi. Please arrange your material and manpower and check your drawing for any services. This is not fixed but based on site condition.




 +60 10-941 8970: @EG MALL Azman as your request





























 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...