Monday, September 4, 2023

05 SEP 23 HKL

SITE GROUP
EG MALL Azman: Good morning..
Site progress photo.
5/09/23.
Basement. Zone 4a. Slab foundation rebar in progress.
 EG MALL Azman: 4th floor. TA1. Slab rebar and formwork in progress.
EG MALL Azman: 6th floor. Z4. Slab formwork and scaffolding.
EG MALL Azman: 6th floor. Z5. Column rebar in progress.
 EG MALL Azman: 6th floor. ZTB1. Column rebar.
EG MALL Azman: 4th floor. Z6. Beam rebar & slab formwork in progress.
EG MALL Azman: Ground floor. ZTB3, TB4. Slab formwork & rebar in progress.


NSC GROUP



 EG MALL Azman: @Leung KH🍀 anything on the retaining wall. Zone 9a. Please double check. Formwork closure in progress.
EG MALL Azman: @HIDAYA KH office Num please double check if any services to install.
HIDAYA KH office Num: Okay
EG MALL Azman: Double check me. Got a pipe sleeve thru the wall to MH20.


Lo. W. H (HKL-Site Engineer): Dear valued NSC, revised basement plan for your immediate attention

 EG MALL Azman: Semua maw ubah... 😭😭
Lo. W. H (HKL-Site Engineer): Ya lo
Dart Econmech: Haha. Sakit mau start final equipment cmni
Edwin Chen 013: Is this final?
Lo. W. H (HKL-Site Engineer): From their drawing they issued always final but never final
Lo. W. H (HKL-Site Engineer): Ya
+60 17-866 0355: beseman GL 2 E
















 