NSC GROUP
EG MALL Azman: Site progress photo.
4/9/2023.
4th floor. TA1. Slab formwork in progress
EG MALL Azman: 6th floor. Zone 4. Slab/scaffolding for 7th floor in progress.
EG MALL Azman: 6th floor. Z5. Column rebar and lift formwork.
EG MALL Azman: 4th floor. Z6. Slab formwork and beam rebar in progress.
EG MALL Azman: @Leung KHπ @Edwin Chen 013 please arrange to move this watertank panel in this 2 days.. we are very urgent to excavate this area. πππ
Leung KHπ: We started relocate on last Saturday, may need your tc team kind assist to full swing work for this ? My team always sitting just wait for our turnππ» Tatqππ»
EG MALL Azman: New casting plan.
Zone 4/a -Basement - 5/9/23
Zone 6 - 4th floor - 6/9/23
Zone TA1 - 4th floor - 7/9/23
Zone TA/2 - 1st floor - 8/9/23
Zone 9/a - ret. Wall. - 8/9/23
Zone TB/3 - GF - 9/9/23
Zone TB/2- 3rd floor-10/9/23
Zone TB/4 - GF - 11/9/23
Zone 4 - 7th floor - 12/9/23
Hi. Please arrange your material and manpower and check your drawing for any services. TQ.
EG MALL Azman: Ini basement. zone 4a.
EG MALL Azman: Retaining wall. 9a.
No comments:
Post a Comment