Site progress photo.
2/9/23.
7th floor. Z4. Slab formwork and scaffolding.
EG MALL Azman: 6th floor. Z5. Column rebar & lift formwork.
EG MALL Azman: 6th floor. ZTB1.
EG MALL Azman: 4th floor. ZTA1. Slab formwork and lift rebar.
EG MALL Azman: Ground floor. TA2. Column rebar
EG MALL Azman: Ground floor. TB3/TB4. Slab formwork.
EG MALL Azman: 1st floor. TA2. Slab scaffolding.
EG MALL Azman: TC are free for lifting.. 👆👆👆
+60 12-843 3877: Installation Trunking -GFL